Project Service Process Timetable
The entire project, from receiving the inquiry from the Ecuadorian customer in November 2021 to the completion of installation and commencement of operations in August 2022, lasted approximately 9 months. Here is the project timeline:
· November-December 2021: Received inquiry from the Ecuadorian customer. After understanding the needs, we provided a project solution based customer’s site conditions and budget.
· January 2022: Signed a contract with the Ecuadorian customer. Upon receiving the deposit, we began production at the factory.
· May-June 2022: After successful production and debugging, we proceeded with packaging and transportation. Upon arrival of the goods at the port near the customer's location, we promptly notified the customer for inspection and pickup.
Beston Rides team also provided online installation guidance for the customer.
· August 2022: Upon completion of installation and debugging of the amusement equipment, the project for the Ecuadorian customer commenced normal operations.